Milestones & Tasks  

Jackpine Oil Sands Mine Expansion
  Shell Canada Ltd.
:  Environmental Assessment
:  Review Panel
  Martin Anderson
:  Active/In Progress


Go to:    
Project stages/phases: PD/PA EA REG FOLW-UP View All
Milestones & Tasks Start Target Completed
Environmental Assessment
1.

Post the Notice of Commencement on the CEARIS

RESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency

2010-12-13   2010-12-13
2.

Post Notice of the Minister of the Environment's referral to a Panel Review on the CEARIS

RESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency

2010-12-13   2010-12-13
3.

Notify Aboriginal Groups that a federal EA is required

RESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency

2010-12-13   2010-12-13
4.

Post draft Joint Review Panel Agreement (JRPA) (including Panel Terms of Reference) on the CEARIS

RESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency
Energy Resources Conservation Board (ERCB), Alberta

SUPPORT
Environment Canada
Fisheries and Oceans Canada
Health Canada
Natural Resources Canada
Transport Canada
Parks Canada

2010-12-14   2011-03-07
5.

Public comment period on the draft Joint Review Panel Agreement (JRPA) (including Panel Terms of Reference)

RESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency

2011-03-07   2011-04-06
6.

Announce availability of Participant Funding

RESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency

2011-03-14   2011-03-14
7.

Notify Aboriginal groups of the availability of Aboriginal Funding under the Aboriginal Funding Envelope (Phase I)

RESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency

2011-03-14   2011-03-14
8.

Award Participant Funding

RESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency

2011-06-09   2011-06-09
9.

Award funding under the Aboriginal Funding Envelope (Phase I)

RESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency

2011-06-09   2011-06-09
10.

Post the final JRPA on the CEARIS

RESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency
ERCB

2011-04-07 23 Weeks 2011-09-20
11.

Announce appointment of panel members on the CEARIS

RESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency
ERCB

2011-04-07   2011-09-20
12.

Consultation on information available on the public registry

  2011-09-21 10.8 Weeks 2011-12-16
13.

Consider comments, determine adequacy of information to proceed to hearings

  2011-12-17   2012-01-30
14.

Submit additional Information Requests to Proponent, if required

  2012-01-30   2012-01-30
15.

Submit response to information request(s) from the Joint Panel, if required

RESPONSIBILITY

LEAD
Shell Canada

SUPPORT
Fisheries and Oceans Canada
Transport Canada

2012-01-31   2012-05-16
16.

Public comment period and government review of additional information from Proponent, if required

RESPONSIBILITY

SUPPORT
Environment Canada
Fisheries and Oceans Canada
Health Canada
Natural Resources Canada
Parks Canada
Transport Canada

2012-05-17 9 Weeks 2012-08-03
17.

Consider comments, determine adequacy of information to proceed to hearings

  2012-08-04   2012-08-16
18.

Announcement of public hearings

  2012-08-17   2012-08-17
19.

Submit written government interventions

RESPONSIBILITY

LEAD
Environment Canada
Fisheries and Oceans Canada
Health Canada
Natural Resources Canada
Parks Canada
Transport Canada

2012-08-17   2012-10-01
20.

Public Hearings

  2012-10-29 4.4 Weeks 2012-11-21
21.

Government interventions in public hearings

RESPONSIBILITY

LEAD
Environment Canada
Fisheries and Oceans Canada
Health Canada
Natural Resources Canada
Parks Canada
Transport Canada

2012-11-07   2012-11-21
22.

Submit Panel Report to the Minister of the Environment

  2012-11-22 12.8 Weeks  
23.

Submit the government response to the Joint Panel Report to Governor-in-Council

RESPONSIBILITY

LEAD
Fisheries and Oceans Canada

SUPPORT
Canadian Environmental Assessment Agency
Environment Canada
Health Canada
Natural Resources Canada
Parks Canada
Transport Canada

  12 Weeks  
24.

Governor in Council decision

RESPONSIBILITY

LEAD
Privy Council Office

SUPPORT
Canadian Environmental Assessment Agency
Environment Canada
Fisheries and Oceans Canada
Health Canada
Parks Canada
Transport Canada
Natural Resources Canada

  8 Weeks  
25.

Post the course of action decision(s) on the CEARIS

RESPONSIBILITY

LEAD
Fisheries and Oceans Canada
Transport Canada

SUPPORT
Canadian Environmental Assessment Agency

  1 Weeks