This is historical information

Historical information is provided for reference, research or recordkeeping purposes, it is not maintained. Visit our Project Inventory page to learn about MPMO’s ongoing initiates. Contact the Major Projects Management Office for additional information.

MPMO Tracker banner

Milestones & Tasks  


Aley Niobium Mine

Proponent:  Aley Corporation Limited
Phase:  Environmental Assessment
Environmental Assessment Type:  Substituted EA
MPMO Officer:  Carolyn Ramsum
Status:  Active/In Progress





Project stages/phases: PD/PA EA REG FOLW-UP View All
Milestones & Tasks Start Target Completed
Project Agreement
1. Receive Project Description ContactsRESPONSIBILITY

LEAD
Aley Corporation Limited

2014-09-30 0.2 Weeks 2014-09-30
2. Scan Project Description ContactsRESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency

2014-10-01 2 Weeks 2014-10-09
3. Accept Project Description ContactsRESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency

2014-10-10 0.2 Weeks 2014-10-10
4. Public comment period ContactsRESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency

2014-10-10 4 Weeks 2014-10-30
5. Determine if a federal environmental assessment is required ContactsRESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency

2014-10-31   2014-11-24
6. Decision on request for substitution ContactsRESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency

2014-10-31   2014-11-24
7. Sign Project Agreement ContactsRESPONSIBILITY

LEAD
Major Projects Management Office

2015-04-22   2015-04-29
Environmental Assessment
1. Post the Notice of Commencement on the CEARIS ContactsRESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency

2014-11-24   2014-11-24
2. Decision on request for substitution ContactsRESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency

2014-11-24   2014-11-24
3. Finalize Application Information Requirements ContactsRESPONSIBILITY

LEAD
EAO

SUPPORT
Canadian Environmental Assessment Agency
Environment Canada
Fisheries and Oceans Canada
Aboriginal Affairs and Northern Development Canada
Natural Resources Canada
Transport Canada

2014-11-25    
4. Submit Application ContactsRESPONSIBILITY

LEAD
Aley Corporation Limited

     
5. Provide draft EA Report ContactsRESPONSIBILITY

LEAD
EAO

SUPPORT
Canadian Environmental Assessment Agency
Environment Canada
Fisheries and Oceans Canada
Health Canada
Aboriginal Affairs and Northern Development Canada
Natural Resources Canada
Transport Canada
Major Projects Management Office

     
6. Provide final EA Report ContactsRESPONSIBILITY

LEAD
EAO

SUPPORT
Canadian Environmental Assessment Agency

     
7. Minister Makes EA Decision ContactsRESPONSIBILITY

LEAD
Minister

SUPPORT
Canadian Environmental Assessment Agency
Environment Canada
Fisheries and Oceans Canada
Health Canada
Aboriginal Affairs and Northern Development Canada
Natural Resources Canada
Transport Canada
Major Projects Management Office

     
8. Issue and Post the Minister's EA Decision Statement on the CEARIS ContactsRESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency

     
Regulatory Decision-Making
Explosive Act License
1. Submission of the Project Description and information on explosives factory(ies) and magazine(s) to NRCan        
2. Determination whether a Licence under the Explosives Act paragraph 7(1)(a) is required        
3. Submission of an application for an Explosives Act Licence        
4. Review of the Application        
5. Request for clarification or additional information        
6. Resubmission of a complete application for an Explosives Act Licence        
7. Review supplier's revised application        
8. Make regulatory decision        
Navigation Protection Act Authorization(s)
1. Navigation Impact Assessment (NIA) process - on-site inspection(s)        
2. Liaise with the Proponent regarding potential works in regards to impacts on navigability        
3. Final application review process        
4. Make regulatory decision        
5. Address public and Aboriginal comments regarding the Project's potential impact on navigation        
6. Deposit and advertise, if required        
7. Submit NPA application(s), including information required to process applications under the NPA, for each proposed work        
8. Notice to the Proponent to advertise pursuant to the NPA, if required        
9. Determination and comment on NPA application(s)        
10. Submit NPA application(s), including information required to process applications under the NPA, for each proposed work