Milestones & Tasks  


Amisk Hydroelectric Project

Proponent:  AHP Development Corporation
Phase:  Environmental Assessment
Environmental Assessment Type:  EA by Responsible Authority
MPMO Officer:  Erika Uchmanowicz
Status:  Active/In Progress





Project stages/phases: PD/PA EA REG FOLW-UP View All
Milestones & Tasks Start Target Completed
Environmental Assessment
1. Post the Notice of Commencement on the CEARIS ContactsRESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency

2015-12-16 0.2 Weeks 2015-12-16
2. Public and Aboriginal group comment period on the draft EIS Guidelines ContactsRESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency

2015-12-16 5.6 Weeks 2016-01-25
3. Refer the EA to a review panel ContactsRESPONSIBILITY

LEAD
Canadian Environmental Assessment Agency

2016-01-26 2.8 Weeks 2016-02-12
4. Finalize the EIS Guidelines and provide to the Proponent   2016-01-16   2016-02-19
5. Submit the EIS and EIS Summary        
6. Review of EIS to ensure the requirements of the EIS Guidelines are met        
7. Public and Aboriginal group comment period on the EIS summary        
8. Federal review and provide comments to the Proponent on the draft EIS        
9. Submit revised EIS or additional information, as appropriate        
10. Review the revised EIS or additional information, as appropriate        
11. Prepare the draft Environmental Assessment Report        
12. Federal review and provision of comments on the draft EAR to the CEA Agency        
13. Public and Aboriginal group comment period on the draft EAR        
14. Finalize the EAR and submit to the Minister        
15. Issue the EA Decision Statement        
16. Post the Notice of the Minister of the Environment's EA Decision Statement on the CEARIS